Tyrrells reinspection booked for tomorrow so lots of jobs today, EB have had two weeks but apparently everything on the Tyrrells report is getting done today...hhmmmm...still no one on-site so will only be half a day really.

To do this afternoon:
roof - bedding of ridge capping & flashing to complete, cleaning the gutter
painting - lots of touch ups & repainting the stairs
tilers to do lots of sealing & will be cleaning the drains - I thought the plumbers did this????
the doors don't close properly so not sure who's doing this????
the bifold doors are rusted apparently the cleaners clean this so not sure this is happening....
windows scratched still to be replaced

If they can do this in one day why didn't they do it two weeks ago????

The one thing that got done was the mosaic tiles - very surprised to see this done and also very surprised how they rectified the issue...The problem was that the tiling was not straight and protruding out plus the tilers couldn't get behind the vanity basin so the tiles were falling off.

EB's solution & Di Lorenzo - this was coming from the General Manager of Di Lorenzo - they tiled over the existing tiles. So you can imagine how thick this is looking...this was an issue in May so they have had at least one month to sort this out and this is how they fixed it.

Di Lorenzo are saying that the tiling should have been done first before the basin went in and that the basin has not been placed correctly it's too far away from the wall. They tiled over the tiles as this is the best option without moving anything....

EB just want the easy fix obviously so have decided to do this without asking us if we agree with it. We did not consent to tiling over tiles we wanted it done properly so if it meant moving the basin then this is what EB should do not this half arsed job....why do we have to constantly fight to get something done properly???? Has anyone heard of doing this to a NEW house - tiling over tiles????

Here are the tiles below which needed to be rectified...so they tiled over this....

Why did I bother paying so much money for these *%$#@ing expensive tiles when this is how they are tiling it????

I feel like we have been taken for a very expensive ride long enough and I just want it to end



1 comment:

Anonymous said...

Eden Brae should be ashamed of themselves. This is NOT quality work, but I know EXACTLY what you mean by wanting this to be over!!!! Building is such a dreadful experience. Thank goodness we will never be doing it again!