According to my fellow blogger 'The Southies" they are hoping to finish by the end of May, so using that deduction we should be in the house in two weeks!!!! Will have to keep guessing as my SS won't give me a timeframe. He did say 'a couple of weeks' today...
Slight hiccup today, the mirrors were installed before the splashback and were placed well below were the tiles were going - so the tiler would have had to cut the tiles around the mirror - would not have been a pretty site; plus we're paying extra for the tiles to be 1.2m - did not really want this cut around...did not make sense anyhooo this is getting sorted thanks to the CM who was very accommodating to sorting this out; The mirrors will need to be moved up above the tiling.
The bed light switches have been sorted too, measured them today as we had no idea where they were being placed - all is ok, not exactly the right spots but at least the switches won't be behind the bed.
There was also a slight hiccup regarding the painting of the woodwork last week, as we wanted the woodwork around the windows a different colour to the internal wall which we specified in our final variation as Crisp White, but for some reason my SS didn't have this variation in his system. I'm very happy that my CSR sorted this out straight away and rectified the issue.
The internal painting still to be completed, the gloss have not been applied; would probably need touch ups also after the powerpoints and switches have been put in.
The tilers were in Mon and should finish tomorrow, can't wait to see my floor tiles and splashback.
EDIT: I thought the electricals had to be done first as they've marked on the floor where things were?? now they're getting covered up because of the tiling? how does that work? I noticed too that the aircon vents have been installed.
New Things, New York & Happy New Year
10 years ago
2 comments:
Our electricals were done over a month ago, they just need to come back to pull out the wiring where appropriate & attache the p/pts, switches, etc...
From behind the tiles??-don't know how that's done!
Congrats on the pace hermyleen.
sorry I meant cutting out where they've done the rewiring already; they've drawn on the floor where these points were put in
Post a Comment