Gyprocking commenced last Thursday (day of hell) most of the gyprocking was completed. Continued late Friday afternoon with plastering over the joins of the gyprock and finished by the wkend. It took 5 men over 3 days to complete this.
photos from today:
http://picasaweb.google.com.au/hermyleenb/Gyprock?feat=directlink
We went on site today with the CM and was relieved to see that the opened windows over the wkend did not result in any damage of the linings, no signs of warping. It was raining quite hard on Sun and as much as I wanted to go on site and close the windows, I refrained as per our contract...
New Things, New York & Happy New Year
10 years ago
No comments:
Post a Comment